Framing and system omissions
Three issues caught before closeout
Incorrect ceiling rafters would have produced the wrong ceiling elevation. Garage windows and fire-suppression sprinklers were also missing. All issues were corrected and the contractors absorbed the cost, but the corrective work is estimated to have added several weeks to the build.
Owner-side lesson: Correction may protect the budget, but owners still bear the disruption and schedule impact of work discovered late.